|
The early South shaft terminated at the Top Hard seam level. When the shaft was deepened in 1920 it was extended to the Black Shale seam but was only worked down to the Deep Hard level and, strictly speaking, the shaft foot was an inset.
The shaft-side roadway width was about the same as the shaft diameter since in the original layout, the tubs arrived and left the shaft side via different roadways, unlike some collieries where the pit bottom was widened out to allow tubs to pass alongside of the shaft.
Post 1922, this shaft operated a three deck simultaneous loading system and the pit-bottom roadway heights reflected that. During the 1950s modernisation the pit bottom was substantially altered with a single decking level constructed a few feet above the original bottom-deck level and the full & empty sides were reversed. The pit bottom brickwork, however, remained largely unchanged.
The layout of the mine-car circuit now required the empty mine-cars to be returned to the full side roadway, and in order to achieve this a brick-lined snicket was driven about 6ft / 2m to the left hand side of the shaft. The empty side was graded to allow the unloaded mine-cars to run past the snicket entry to an automatic pneumatic reversal ram which propelled them back via switch points into the snicket onto a Lofco chain creeper which carried them along the gradually rising track until they could gravitate toward the loading point.
|