2008
Site:
Infrastructure:
The installation of the 3 phase mains electrical supply has been completed. Discussions are taking place to determine how to undertake the migration of the old electrical installation onto the new supply.
A number of weather-proof fluorescent lighting fittings have been acquired and these are being overhauled ready for installation in the South pit-top and engine-house basements.
Pit tops:
At the South pit-top, considerable progress is being made on tidying up on the full-side.
On the empty side, a display of various tools etc has been constructed.
The renovation of the shaft air-doors and their framework continues.
The mine-car loading ram and catch restoration is making good progress.
The motor from the empty-side turntable has been removed for overhaul.
The flooring into the empty side has been made up to improve accessability.
Winders:
In the South engine-house work continues steadily on the Markham engine and on the drum in preparation for its shot-blasting and painting.
The Robey brake pillars have been completely dismantled and cleaning / painting proceeds steadily. The two brake units on the shaft side of the drum are now in the process of being re-erected.
One hydraulic brake release ram has been dismantled and found to be in excellent condition.
Engine-houses:
|
|
|