22/2/08
The mains electricity supply has been installed and commissioned. Many thanks to EMDA, their project consultant Alex Gibson at Wm. Saunders Partnership and to Glyn Davies at Sherwood Consulting Engineers who did the design & specification work.
The next stage is to migrate the existing circuits from the diesel generator onto the new supply.
|