2007
Site:
The derelict land to the south of the pit-tops, where the east railway-sidings, the baths, cooling ponds, workshops and the main offices once stood, has been cleared and landscaped.
A new access road with gated entrances has been constructed and car-parking provision provided. Hedgerows and a number of young trees have been planted.
The pit-tops have been tidied and much needed revenue created by the scrapping of old steelwork.
Infrastructure:
A preparatory survey and report on the electrical installation has been produced and planning is in progress for the installation of a 3 phase mains electrical supply.
The long awaited mains water supply has finally arrived in the “mess-cabin”. At first a trickle and then - well certainly not a torrent, but acceptable.
Pit tops:
At the South pit-top, the shaft block-work has been completed and back filled.
Considerable progress has been made with the renovation of the full-side shaft-doors.
Work is in progress on the mine-car loading rams and catches.
Winders::
In the South engine-house work continues steadily on the Markham engine and on the drum in preparation for its shot-blasting and painting.
The reversing cross-shaft has been withdrawn from under the RH cross-head guide and this has enabled the dismantling of the rear Robey brake pillars to proceed.
Engine-houses:
Metal racking has been installed in the South engine-house to hold dismantled components which previously were on the floor.
Safety fencing has been erected around the North winder to restrict public access.
|
|
|