2000

  • 2nd May: Work commences on the new roof for the North engine-house.
  • Re-assembly of the North winder heavy engine components.

2001

2002

  • Renovation work on North winder valves progressing.
  • 14th May: Work commences on removing lagging from pipework.
  • 1924 Robey winding engine and drum from Westhorpe delivered to Pleasley.

2003

2004

  • 19th Dec: After 18 years, the North winder is the turning again.

2005

2006

2007

 